Nam Sam 3 is totally ready for "The campaign of 90 days and nights to complete the main Dam to the elevation 536m"

 

The Director of SCI E&C Joint Stock Company has just signed the Decision launching the construction Campaign at Nam Sam 3 Hydropower Project in Houaphanh,Laos. The Campaign will take place from April 01,2022 to June 30,2022 with the target of accelerating the completion of RCC concrete to the elevation 536m of main dam before the upcoming rainy season.

With 14 teams and the manpower of 500 of workers and engineers, Project management board of Nam Sam 3 is entering the peak construction days. In order to ensure the safety of manpower and machinery and meet the committed progress requirement with the owner, SCI E&C Joint Stock Company is now issuing the Decision launching "The campaign of 90 days and nights to complete the main Dam to the elevation 536m".

sci_le_phat_dong_xm

The Campaign will take place in 90 days, constructing the main dam of Nam Sam 3 Hydropower Project from elevation 521m to 536m. The first stage of the Campaign will start from April 01,2022 to May 15, 2022 with the target of completing elevation from 521m to 528.5m of the dam with 74.000m3 RCC. The second stage of the Campaign will start from May 16,2022 to June 30,2022 with the target of completing elevation from 528.5m to 563m of the dam with 90.000m3 RCC. The employees will be awarded under the Campaign "90 days and nights to complete the main Dam to the elevation 536m" by the Bonus and Welfare Fund of SCI E&C Joint Stock Company.

Mr. Nguyen Chinh Dai, Director of the Company said: "Nam Sam 3 Hydropower Project is considered as an important project needed to accelerate in 2022. Therefore, we have been arranging the maximum resources of manpower with the additional engineers, expert in hydropower and a sufficient amount of cement, steel and other materials available at site facilitating putting the work on time ensuring the committed progress. Hopefully this will be the motivation for workers, engineers of Nam Sam 3 to accelerate the construction progress".

Leader who directs the construction of main Dam, Chief Engineer Luu Minh Thanh, said: "This is a timely campaign of company’s leaders to motivate employees to ensure the construction progress. Because it will be the rainy season in the early of July, we will encounter many difficulties during the pouring concrete process at the current elevation. Not only conveying material, but ensuring the safety of manpower and machinery during this stage are extremely difficult" Mr. Luu Minh Thanh confirmed that SCI will make every effort to meet the campaign target on June 30, before the rainy season.

The main Dam of Nam Sam 3 Hydropower Project is processed by SCI E&C using RCC technology – the most advanced roller compacted concrete. The main Dam with 907.406m3 RCC with the height HMax – 121.7m and the crest length of 321.4m. In 2022, SCI E&C aims to complete 75% of the main dam of the project.

 

 