News

03

03-2022

Huong Linh 4 wind farm accelerated from the beginning of the year

Huong Linh 4 Wind Power Plant with a capacity of 30MW and a scale of 10 turbines undertaken by SCI Group is in the highly concentrated phase of completion. Especially in the early days of March, the 110kV transformer station and transmission line are being accelerated implementation progress.

Identified as an important wind farms project of SCI Group in 2022, since winning the contract, SCI has focused on human and material resources to meet the schedule and ensure the quality of the work.
huonglinh_tangtoc_1
SCI workers on site

Hundreds of engineers and workers were mobilized to serve the project. Equipment gathered here includes many new vehicles such as rollers, bulldozers, excavators, graders, irrigation trucks and dozens of specialized trucks carrying materials.

Construction in the context of the complicated developments of the Covid-19 epidemic, SCI Group and the Employer always consider both production and safety as a top priority.

Mr. Nguyen Ngoc Hoai - Head of Technical Quality Department said: 'The Huong Linh 4 project is an important project of SCI in Quang Tri. Therefore, the project schedule is set very tight. With the great determination of the Employer, after nearly 5 months of construction, the project has completed 5/10 of the concrete foundation for the turbine.

The road construction and operation have basically completed the excavation and backfilling of the routes'.

According to Mr. Hoai, in March, SCI will complete and install the substation equipment, complete the erection of the 110Kv power transmission line and at the same time deploy the 22Kv line work item.

 

huonglinhtangtoc_1
Engineers, wind power experts working on Huong Linh 4 construction site

Mr. Pham Xuan Duong - Director of the project management board affirmed 'With the high spirit and determination of SCI workers, they do not falter in the face of difficulties and challenges. We will focus our resources and hand over construction items on schedule and with quality assurance for the installation of wind turbines for the purpose of power generation that the Employer has set out.

Huong Linh 4 wind power plant is expected to add about 100 million kWh of green energy annually to the national power source. Completing the items on time and ensuring quality is also the most obvious commitment to the ability of SCI Group's team of experts and engineers in large-scale wind power projects.

 

Back