SCI Group simultaneously began various projects in early spring

In order to ensure the project progress as well as encourage the working spirit of the employees, starting from February 2 to 07, 2022, SCI Group simultaneously launched in all the projects under construction.

___n_51

At Nam Sam 3 Hydropower Project (Laos), Mr. Luu Minh Thanh - Vice Chairman of the project in charge of construction said: "The Lunar New Year holiday of our project was from the afternoon of the 30th to the end of the 1st. On the morning of the 2nd, we started the new year in the spirit of excitement from all of workers".

___n_50

In this launch, Nam Sam 3 project focuses on items such as: RCC of main dam from elevation +512 to +515m; Continue to complete the construction of the deep draft tube to the elevation of +515m; Digging the foundation pit which remains 25% (completed 75%); Continuing construction of downstream discharge canal excavation (60% completed); Installation of complete distribution station; Completing the leveling work of the operation management building.

___n_54

At the Nam Lum 1 and 2 Hydropower Projects (Lai Chau), employees on the site started out from the afternoon of the 6th of the Lunar New Year. Mr. Trinh Van Chan - Head of Technical Planning Department at the project said: "In the spirit of urgency, although this year we have to go to work earlier than usual, we still strictly comply and ensure attendance at the project. accordance with company regulations. Arriving at the project at noon, in the afternoon, we deloy the work."

 

It is known that the focus of Nam Lum Project is still implementing the construction of water tunnels, completing the construction of Nam Lum 1 factory and Nam Lum 1 dam. Production of aggregates of rock and sand for the project's concrete. : "The goal is to complete the factory construction and hand over the equipment for installation before April 30," shared Mr. Trinh Van Chan.

 

___n_48

Like the Nam Lum Project, the Nam Xe Hydropower Project (Lai Chau) also launched on the afternoon of the 6th day of the Lunar New Year to dig the foundation pit of the second phase of the factory.

 

Mr. Pham Son Tung - Vice President of the project in charge of construction said: "It rained heavily on the afternoon of the 6th, but the staff and employees were still enthusiastic about going to the army at the beginning of the year to get lucky. Hopefully, with this spirit of determination, 2022 will be the year that our company achieves more success."

 

___n_46

At Huong Linh 4 Wind Power Project (Quang Tri), employees started working from the morning of the 7th day of the Lunar New Year.

 

Mr. Pham Xuan Duong - Vice President of the project in charge of construction said: "Our employess who returned to Tet have come back almost enough, except for some people who have an unexpected job, are also comfortable starting work from the 7th. .

 

Currently, the project is focusing on construction: Turbine foundation; 110KV substation; 110 KV line; Construction and operation route”.

 

It is known that Huong Linh 4 wind power project has basically completed concrete construction of 4/10 foundations; The 110 KV transmission line column have been completed with 100% concrete foundation, 22/41 columns can be erected; The substation has basically completed the rough part, the finishing part is under construction.

___n_53

Working ardently but not forgetting the task of preventing Covid-19, the workers who return to the site after the Tet holiday will be arranged by the projects in a medical isolation area in accordance with regulations.

Wishing all employees of projects under construction in particular and the entire SCI Group in general, a new year of prosperity, a myriad things go according. Wish SCI Group continue to achieve positive results like the past years.