Namtheun 1 Hydropower Plant
-
Investor
Phonesack (Lao), CSE (Lao), EGCO (Thailand), EDL-GEN (Lao PDR)
-
Place
Bolikhamxay Province, Lao PDR
-
Execution time
2017 - 2019
-
Scale
650MW
-
Work
Construction of Crushing Plant, Batching Plant; Access Roads; Quarry Stripping, Excavation & Hauling with total quantity of 4,800,000m3; Excavation, Embankment of Main Dam's Right Bank; RCC Upstream and Downstream Cofferdams; Quarry Rocks Exploitation & Blasting.